Mep Work Progress Report Sample Guide
MEP trades must work in tight spaces (ceiling voids, service shafts) and follow a strict sequence. For example, large ductwork must be installed before smaller water pipes or electrical conduits.
First-fix slab conduiting completed up to Level 7. Wall chasing and conduit installation for switch boxes completed on Levels 2 and 3. mep work progress report sample
Upcoming milestones and their planned vs. actual dates (e.g., "BMS Testing Start"). ProjectManager 5. Procurement and Material Status On-Site Material: MEP trades must work in tight spaces (ceiling
Commencing cable pulling for the main electrical risers and resolving the coordination clash between HVAC ducts and drainage lines on Level 4. 2. ENGINEERING & PROCUREMENT STATUS Item Description Target Date Actual Date Status / Remarks Level 5 Combined Coordination Drawings May 10, 2026 May 12, 2026 Approved with Comments (Code B) Fire Pump Set Material Approval May 15, 2026 May 14, 2026 Approved (Code A) Chilled Water Pumps Delivery to Site May 22, 2026 May 24, 2026 Delivered & safely moved to B1 Pump Room Main Switchgear (MDB) Factory Test June 05, 2026 On Schedule; inspector mobilized 3. PHYSICAL PROGRESS BREAKDOWN 3.1 Mechanical & HVAC Works Wall chasing and conduit installation for switch boxes
Owners and project managers need to know exactly where the project stands compared to the schedule [1].
Status of technical compliance submissions.
Delay in the delivery of fire-rated dampers for the kitchen exhaust system (expected next Tuesday).